Weekly Roadwork Report – TxDOT Atlanta District For Nov. 17-23, 2019

Road Construction Ahead

Bowie County

SH 8 – At Sulphur River, replacing bridges.

Camp County

None

Cass County

FM 3129 – From US 59 to SH 77, resurfacing highway.

SH 8 – At Sulphur River, replacing bridges.

Harrison County

I-20 – At Ferguson Creek, FM 3251 and FM 968, conducting preventative maintenance work on bridges.

FM 451 – From 0.6 mile east of FM 31 to FM 9, resurfacing highway.

I-20 Frontage Road – From US 259 to Loop 281, repairing and resurfacing highway.

SH 43 – From Loop 390 to Haggerty Creek, repairing and resurfacing highway.

US 59 – From Marion County Line to Woodlawn Oaks Road, installing median barrier.

Marion County

US 59 – From FM 2208 to Harrison County Line, installing median barrier.

Morris County

SH 49 – From Titus County Line to FM 144, repairing and resurfacing highway.

Panola County

SH 149 – At SH 315, constructing overpass and widening highway.

US 79 – From US 59 to Mill Creek, resurfacing highway.

US 59 – at SH 149, concrete pavement replacement. East side entrance and exit ramps closed. Detours in place.

Titus County

US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.

FM 899 – At Dragoo Creek, replacing bridge. Highway closed to through-traffic.

SH 49 – From FM 1735 to Morris County Line, repairing and resurfacing highway.

Upshur County

None

Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Marcus Sandifer, Public Information Officer, TxDOT Atlanta District, 903-799-1306, marcus.sandifer@txdot.gov.

Comments are closed.